I. Documentation of
equipment to be evaluated.
a. Pump and Motor Identification,
assign unique ID numbers
b. Determine run time for each piece
of equipment
(a. And b. part of preliminary meetings, review of
existing documents/drawings, and plant tour)
c. Pump and motor nameplate
information
c. For wells, determine water level
and amount of draw down
d. Construct a simplified flow diagram
of the facility
1. Pumps
2. Discharge Check Valves
3. Pressure tap locations
4. Discharge measuring points
5. Wiring Components
a. No load voltage measurements
(equipment de-energized)
b. Three phase-to-phase readings
(reference point)
c. Measure inside pipe diameter
a. Install temporary Ultrasonic Flow
Meter if possible or estimate
flow from a fill and/or draw down
test using a tank or clearwell or by other means, based on specific site
conditions.
b. Install calibrated pressure test
gages
c. Record suction and discharge pressure and
reference elevation values
d. Determine flow rate and compare with flow rate
provided by the permanent plant
flow meter
a. Determine Power (Kw) from meter, if
dedicated meter available
(time revolutions, Kh factor, and scaling factor for calculations)
b. In no dedicated meter, compute Kw
using two-wattmeter method
a. Measure voltage and current on
three phases (energized)
using portable electric power meters (< 600 volt equipment)
b. If equipment is greater than 600 volts, estimate
power using plant permanently installed motor current indicators and PSAT
software or using measurements of power on the secondary side of permanently
installed current transformers.
Summary
of Electrical Parameter Measurements and Calculations:
1.
Total power (Kw) from meter or two wattmeter calculations (record)
2.
Individual phase currents (portable meter and CT’s)
3.
Individual phase-to-phase voltages (portable meter, record)
4.
Calculated Apparent Power
![]()
5.
Power Factor (ratio of total to apparent power) calculate and record
![]()
a. Motor Nameplate Data, Efficiency
Rating in percent
b. Measured electric power (Kw)

![]()
Important
especially if Adjustable Speed Drive (ASD)
(manual
setting for consistent speed or use pump affinity laws to compute)
a. Use an adjustable stroboscope to
obtain rotational speed. Speed is generally a low priority item and will only
be measured if requested.
Data on flow rate, pressure, motor
current, and power data are evaluated using the Pumping System Assessment Tool
(PSAT), a software program developed by the U.S. Department of Energy and
endorsed by the Hydraulic Institute.
Output from the program will identify areas where the greatest potential
energy savings can be found.
Among the results of the PSAT analysis is a
comparison of existing annual cost of pump operation with that of an optimal
pump and motor operating under the same conditions. If manufacturers
performance curves are available, the measured performance will be compared to
the like-new performance. Informed
decisions can then be made if equipment repairs are needed or if replacement of
pumping equipment is being considered.
Estimates of payback periods for system
modifications will also be provided to assist the facility in justifying
expenditures. Previous experience has
shown that substantial amounts of energy savings are available in many pumping
systems (20% to 50% and more). A payback period of one to three years is
common, more than justifying the cost of an assessment and the capital expenses
required to implement changes in the pumping system.
Study results are documented in a
comprehensive final report complete with infrared images on CD-ROM. Data collected provide a baseline of
information that can be used to benchmark equipment for future evaluations and
to document energy savings once changes are implemented.
The following services can be provided for a more comprehensive evaluation and should be included in the initial evaluation of each facility.
(Monitor
switchgear, motors, and pumps)
a. Digital Pictures of equipment, associate data
with photo
b. Document physical Piping Layout
c. Identify Electrical Components of pumping system
a. Collect digital and infrared image
of electrical panels
b. Collect digital and infrared images
of motors
c. Document hot spots or anomalies for
further study
a. Monitor vibration in two radial
planes on upper and lower bearings
b. measure axial vibration using the
5-Point Approach
c. measure vibration of pump
mechanical seals
d. Check bearing models versus
database values to determine
bearing fault frequencies
e. Record lubricants and oils used
f. Sample oils for metals and particle
count data
g. Conduct Electric Signature Analysis